Updates From Twitter

Follow for up to the minute alerts.

Design Options for Breaches
Newsletter

Bonner Bridge Update Newsletter
Dec. 2013

Bonner Bridge Update Newsletter
Feb. 2013

Project Fast Facts
  • Status: Projects Under Development
  • County: Dare
  • Type of Project: Bridge Construction
  • STIP Number: B-2500 A,B
Related Links
Bonner Bridge Projects

Description

NCDOT is working to provide long-term solutions for the two breaches caused by Hurricane Irene in August 2011 along N.C. 12 on the Pea Island National Wildlife Refuge and in Rodanthe. This work is considered Phase II of the Bonner Bridge Replacement Project.

Latest News and Updates

N.C. 12 Update 1/14/14

  • Rodanthe Bridge
    NCDOT held public meetings on January, 7, 8 and 9 in Ocracoke, Rodanthe, Buxton and Manteo to present two alternatives for the long-term Rodanthe bridge and gather feedback.

Meeting attendees were given the following handout: Jan 2014 Hearing Handout

A formal presentation that explains the handout was given at the public hearings. The video of the presentation given in Buxton can be viewed here.

The PowerPoint presented at the hearings is available here.

Alternatives

Bridge Location in Pamlico Sound:

Map of alternative

Visualization - Refuge looking south

Visualization - Near Cobina Dr. looking west at the Pamlico Sound

Bridge Location within Current Easement:

Map of alternative

Visualization - Cobina Dr. looking north

Visualization - Green Lantern Court looking north

Visualization - Refuge looking south

An Environmental Assessment (EA) for the Rodanthe project can be reviewed here. Hard copies also are available at several locations along the Outer Banks (see the list in the December 2013 newsletter).

A comment sheet is included at the back of the handout, along with information on how to submit comments. All comments will be taken into consideration and carry equal weight, regardless of how they are submitted. Comments are due to NCDOT by Friday, January 24, 2014.

The department advertised the design-build project on Nov. 1. The design-build teams will be shortlisted after public input is considered and a decision is reached, which is anticipated to be made early 2014. The contract is scheduled to be awarded in late spring/early summer 2014.

  •  Pea Island Bridge
    NCDOT awarded a contract on November 27, 2013, to build a permanent bridge where the temporary one now stands on Pea Island. The contract was awarded to Parsons Construction Group Inc. of Greenville, SC. for $79.7 million. Construction on the new bridge can begin as early as Jan. 6, 2014. The new bridge is scheduled to open to traffic in spring 2016. As part of the bid, the contractor committed to completing the work within 800 calendar days and pay $5,000 per day for any days over 800.

News Releases

  • Currently, no recent news releases.

Project Background and Purpose

The process to implement long-term solutions for the two breaches on N.C. 12 is a continuation of work already under way as part of the Bonner Bridge Replacement Project.

Phase one of the project involves replacing the 2.7-mile bridge over Oregon Inlet, which is currently in the design stage. The project also includes an active coastal monitoring program that uses scientific data to determine what types of improvements are needed on N.C. 12 between Oregon Inlet and Rodanthe and when that work will occur.

Using this program, NCDOT is enacting phase two of the project, which will implement long-term solutions for the parts of N.C. 12 damaged by Hurricane Irene. These long-term fixes will replace the temporary fixes put in place immediately after the storm hit to restore traffic to the Outer Banks.

NCDOT met with a panel of coastal engineers and scientists in October 2011 to get their input on the department's future plans for N.C. 12. NCDOT has compiled a report of the key findings and recommendations provided about topics, which include:

  • Changes in the coastal conditions resulting from Hurricane Irene;
  • Potential long-term transportation options for the two breach sites; and
  • Recommendations on future coastal studies for the northern end of Hatteras Island.

The department is using their input to help guide its decision-making process, regarding N.C. 12.

NCDOT met with citizens in Manteo, Rodanthe and Ocracoke in December 2011 and January 2012 to discuss possible design options for these long-term solutions.

The department continues to work diligently with its state and federal agency partners on the environmental work required to implement the permanent solutions at the two breach sites.

  • On Pea Island, NCDOT is moving forward with its preferred alternative, building a permanent bridge within the existing easement where the temporary bridge is currently located. The department awarded a contract for construction at the Pea Island breach in November 2013.
  • In Rodanthe, the department is considering two options. The first one includes elevating N.C. 12 onto a bridge within the existing easement, which would end just north of the community center and not require beach nourishment. The second option is constructing an approximately 2.5-mile bridge that would extend into the Pamlico Sound and connect back to Rodanthe just north of the community center. NCDOT plans to award a contract for construction at the Rodanthe breach in late spring/early summer 2014.

Environmental Documents

Environmental Assessment for Rodanthe Long-Term Improvements (Project B-2500B), December 2013:

Record of Decision for NC 12- Pea Island Long-Term Improvements (Project B-2500A), October 2013.

Public Comments on the February 2013 B-2500A EA.
General public comments:

E-mails and written comments received in response to a Defenders of Wildlife request of its members:

North Carolina Conservation Network petition:

E-mails and written comments received in response to a Citizens Action Committee to Replace the Herbert C. Bonner Bridge request of its members and friends

Environmental Assessment for Pea Island Long-Term Improvements (Project B-2500A), February 2013:

The EA refers to previous environmental documents that were completed for the Bonner Bridge Replacement Project, including the 2008 Final Environmental Impact Statement, 2010 Environmental Assessment and 2010 Record of Decision. Those documents can be found in the Archives section of the Bonner Bridge Replacement Project webpage.

Supporting Technical Reports to the EA:

Public Hearing Maps for Pea Island Long-term Improvements (Project B-2500A), March 2013:

Public Hearing Maps for Rodanthe Long-term Improvements (Project B-2500B), January 2014:

Project Videos & Photos


These images show the damage to N.C. 12 from Hurricane Irene and the work crews have done to temporarily fix the breaches.


Before & After Photos

Place your mouse over the image below to see the contrast of each breach site before and after NCDOT made temporary repairs.


These videos highlight the work NCDOT did to restore traffic to the Outer Banks quickly after Hurricane Irene. The temporary fixes the department put in place after the storm hit helped reinstate the area’s economic lifeline.

Click on the thumbnail images to view each video.

Contact Information

Beth Smyre, P.E.
Project Planning Engineer

  • Email: Contact Us
  • Phone: 919-707-6043
  • Address: 1548 Mail Service Center, Raleigh, NC 27699-1548

John Page
Project Manager, Parsons Brinckerhoff

  • Email: pagej@pbworld.com
  • Project Hotline: 1-866-803-0529
  • Address: 434 Fayetteville Street, Suite 1500, Raleigh, NC 27601

Resources for Local Property Owners

In many cases, it is inevitable that a certain amount of private property must be acquired. The displacement of homes and businesses is minimized to the extent practicable. The following brochures will answer questions about this process.