  • The existing drawbridge will be replaced on new alignment with a 65-foot high fixed-span bridge.
  • U.S. 70 is being rerouted from downtown Beaufort to a new location.

  • The existing culverts under Turner Street are being replaced with a bridge. Sidewalks along both sides of Turner Street will connect downtown Beaufort to the new U.S. Highway 70.

News and Updates

  • The channel span installation began June 1, 2016, reducing the channel's navigable height to 65 feet.
  • Traffic will be placed on the newly constructed bridge on January 27, 2018.

  • The existing bascule drawbridge over Gallants Channel will be closed to traffic on January 27, 2018.

  • Turner Street was closed in June 2015, and work to replace the culvert pipes with a new bridge is in progress and should be completed by April 1, 2018.

  • The final four-lane traffic pattern for the new alignment of U.S. 70 is expected to be in place by June 2018.

  • Removal of the old bascule drawbridge is expected to be complete by June 2018.