Project Maps

Project Map

Project Map

Environmental Features Map

Project Fast Facts
  • Status: Projects Under Development
  • County: Wake
  • Type of Project: Widening
  • STIP Number: U-2719
  • Estimated Cost: $450 million to $475 million
  • Property Acquisition Start: 2018
Videos

I-440 Improvements Project Update
(July 18, 2017)

I-440 Improvements Logo

Project Overview and Purpose

Improvements to I-440 – between just south of Walnut Street in Cary and north of Wade Avenue in Raleigh – are needed to improve traffic flow, access and efficiency along the roadway (referred to locally as the Raleigh Beltline).

Changes include widening I-440 from four to six lanes, replacing pavement and bridges and upgrading interchanges.

This segment has four through lanes and forms a "bottleneck" between the six through lanes on both ends, causing congestion, which is forecast to increase.

Built in the 1960s, it is also oldest section of I-440 and is in need of rehabilitation. The roadway and interchanges have substandard design elements, such as poor sight lines, narrow shoulders, narrow medians and short acceleration/deceleration lanes.

Project Highlights

The N.C. Department of Transportation, in cooperation with the Federal Highway Administration, has completed an environmental assessment of the proposed improvements to I-440.

An Environmental Assessment, which contains a summary of the impacts and benefits associated with the preliminary project designs – referred to as detailed study alternatives – was signed June 26, 2017.

NCDOT then held an open house and public hearing on Aug. 8, 2017, to give the public the opportunity to ask questions about the project, and to comment on the design maps and environmental assessment.

The NCDOT project team will review all feedback and explore options to incorporate and address concerns where and when feasible.

Project Cost

This project is listed as U-2719 in the N.C. Department of Transportation's State Transportation Improvement Program and is funded for $450 million to $475 million.*

*Estimated costs are subject to change.

Project Timeline

Milestone Dates*
Detailed Study Alternatives finalized Early 2017
Preliminary design complete Early 2017
Public hearing Aug. 8, 2017
Environmental study finalized with
anticipated Finding of No Significant Impact
2018
Right of way acquisition begins 2018
Construction begins as design-build contract 2018

*Future dates are preliminary and subject to change.

Project Documents

Environmental Assessment & 2017 Detailed Study Alternative Maps

Nov. 12, 2014 Public Meeting Materials

Other Documents

Contact Information

Jill Gurak, P.E.
(919) 431-5298
Send a message
1616 East Millbrook Road
Suite 160
Raleigh, NC 27615

Jamie Lancaster, P.E.
Project Executive
Projects Priority Unit
(919) 707-6620
Send a message
1595 Mail Service Center
Raleigh, NC 27699-1595

Resources for Local Property Owners

Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.