Planned Construction Activities

​​The following are planned construction activities on the improvements to U.S. 17 Business and the replacement of the Perquimans River Bridge, known as the “S-Bridge,” for April 2020. 

Please note that construction activities may vary and are highly dependent on equipment and weather.

Current Project Proceedings

Pile Driving – Piles will continue to be driven from the temporary stone road adjacent to the causeway. ​​

Concrete Operations – Pile caps will be constructed on the installed piles, and the walls to construct the top level of the control house will be erected.

Earthwork – Wick drains are to be installed near the new bridge's south approach to encourage soil consolodation. ​ ​