Busy Week Ahead for I-85 Project in Rowan County

SALISBURY – Contract crews have planned several lane and ramp closures for next week as part of the Interstate 85 rehabilitation project.

The following closures will be in place between 8 a.m. and 9 p.m. while diamond grinding work continues along the I-85 corridor near Salisbury.

Monday: The two right lanes of I-85 North will be closed between Exit 76 (Innes Street) and Exit 79 Exit 79 (Spencer/Old Union Church Road).

Tuesday: The two right lanes of I-85 North will be closed between Exit 76 (Innes Street) and Exit 79 (Spencer). Also, the ramp from I-85 North to Exit 79 (Spencer/Old Union Church Road) will be closed. Drivers needing to access this exit will continue on I-85 North to Exit 81 (Long Ferry Road) and take I-85 South back to Exit 79.

Wednesday: The two right lanes of I-85 South will be closed between Exit 79 (Spencer/Old Union Church Road) and Exit 76 (Innes Street). Also, the ramp from Exit 79 (Spencer/Old Union Church Road) onto I-85 South will be closed. Drivers needing to access I-85 South will take I-85 North to Exit 81 (Long Ferry Road) to turn around.​

Thursday: The two right lanes of I-85 North will be closed between mile markers 78-80. Also, the ramp from Exit 79 (Spencer/Old Union Church Road) onto I-85 North will be closed. Drivers needing to access I-85 North will take I-85 South to Exit 76 (Innes Street) to turn around.

​All of this work is weather dependent and subject to change. Drivers should slow down and anticipate crews working close to the travel lanes throughout this work zone.

***NCDOT***

2/26/2021 4:15 PM