Extended Lane Closures Scheduled for Beaufort County Bridge

​WASHINGTON – The N.C. Department of Transportation will conduct continuous lane closures on a major Beaufort County bridge over the next two years. 

On Monday, crews will begin bridge preservation work along a portion of U.S. 17 that connects Washington to Chocowinity. The 16-year-old bridge crosses over U.S. 17 Business and the Tar River. This preservation work is part of routine maintenance to maximize the lifespan of the structure.

Crews will begin by altering the existing pavement markings. Once installed, the inside lanes in both directions will close first, leaving the outside lanes open to traffic. Once interior lane work is completed, the outside lanes will close and the inside lanes will open to traffic. 

Through traffic will be maintained for the duration of the project. Work is expected to last until summer 2028.

Drivers should use caution when traveling through the work zone and plan for increased travel times.

For real-time travel information, visit DriveNC.gov or follow NCDOT on social media.​