Watauga County Bridge Replacement Seeing Steady Progress

Road construction scene featuring workers in reflective clothing smoothing fresh asphalt on a highway.

​Crews smooth fresh asphalt on N.C. 105 near the Watauga River.​

BOONE – Drivers should prepare to see construction activity on N.C. 105 this week as the first phase of an N.C. Department of Transportation bridge replacement project nears completion in Watauga County. 

Crews from Wright Brothers Construction have finished most paving operations for the first phase of the project replacing the bridge on N.C. 105 over the Watauga River

Over the next several weeks, crews may reduce traffic to a one-lane pattern on N.C. 105 near the Watauga River from 9 a.m. to 4 p.m. Mondays through Thursdays to finish construction activities like guardrail installation, signal coordination and pavement marking installation. 

Flaggers and law enforcement officers will direct traffic during closures. 

Motorists should allow additional travel time, avoid distracted driving and obey posted signs and flaggers.

Transportation officials expect to shift traffic to the new bridge later this summer. Once traffic is shifted to the new bridge, crews will remove the existing bridge and build the rest of the new bridge in its place. 

The entire $48.7 million project​ is anticipated to finish in late 2027.