skip to main
Close Menu

Project Highlights

​​The project, as shown in the chart below, is divided into five sections and includes segments of roadway that are complete, under construction or in the planning stages.

Location​Section​STIP Number​Status
​U.S. 401 Business/Ramsey Street to All American Freeway​Section DA​U-2519DA​Complete
​All American Freeway to Cliffdale Road​Section CB​U-2519CB​​Under construction
​Cliffdale Road to U.S. 401/Raeford Road​Section CA​U-2519CA​Design-build contract underway
U.S. 401/Raeford Road to Camden Road ​Section B​U-2519BA
U-2519BB
​In development
​Camden Road to I-95​Section A

​U-2519AA  U-2519AB

​Design-build contract underway

U.S. 401 Business/Ramsey Street to All American Freeway

Work on the Fayetteville Outer Loop (I-295) from U.S. 401 Business/Ramsey Street to All American Freeway – referred to as Section DA – is being completed in three stages:

  • I-295 from Ramsey Street to Murchison Road, which was completed in August 2016
  • I-295 from Murchison Road to Bragg Boulevard, which was completed in August 2014
  • I-295 from Bragg Boulevard to All American Freeway, which was completed in December 2016

All American Freeway to Cliffdale Road

Referred to as Section CB, I-295 from All American Freeway to Cliffdale Road is under construction and expected to open to traffic in the fall of 2019.

Cliffdale Road to U.S. 401/Raeford Road

The N.C. Department of Transportation awarded an $85.2 million design-build contract in June 2016 to the project team of Barnhill Contracting Co., Sanford Construction and HDR Engineering for work on Section CA, a 3.1-mile stretch from Cliffdale Road to U.S. 401/Raeford Road.

Design-build allows all aspects of a project from design through construction to be completed under a single contract.

Work also includes replacing the Lake Rim Runoff bridge on Old Raeford Road over Bones Creek.

Construction is underway on the Lake Rim Runoff bridge, and construction for the Outer Loop section is scheduled to begin as early as August 2017. It is expected to be completed by August 2022.

U.S. 401/Raeford Road to Camden Road

Design and right-of-way acquisition are underway for work on Section B – U.S. 401/Raeford Road to Camden Road. This segment is scheduled to be awarded a construction contract in July 2020, with constructing starting in fall 2020. Completion date is TBD.

Camden Road to I-95

In December 2017, a $129.7 million design-build contract was awarded to the Wilmington-based team of Balfour Beatty Infrastructure Inc., Branch Civil Inc. and STV Engineers Inc. The team will design and build Section A – Camden Road to I-95 – with a scheduled completion by July 2021.

5/22/2019 5:57 PM