skip to main
Close Menu

Project Highlights

​​​​​​​​​The project, as shown in the chart below, is divided into five sections and includes segments of roadway that are complete, under construction, or in the planning stages.

Location​Section​STIP Number​Status
​U.S. 401 Business/Ramsey Street to All American Freeway​Section DA​U-2519DA​Complete
​All American Freeway to Cliffdale Road​Section CB​U-2519CB​
Complete
​Cliffdale Road to U.S. 401/Raeford Road​Section CA​U-2519CA​Design-build contract underway
U.S. 401/Raeford Road to Camden Road ​Section B​U-2519BA
U-2519BB
​In development
​Camden Road to I-95​Section A

​U-2519AA  U-2519AB

​Design-build contract underway

U.S. 401 Business/Ramsey Street to All American Freeway

Work on the Fayetteville Outer Loop (I-295) from U.S. 401 Business/Ramsey Street to All American Freeway – referred to as Section DA – was completed in three stages:

  • I-295 from Ramsey Street to Murchison Road, which was completed in August 2016
  • I-295 from Murchison Road to Bragg Boulevard, which was completed in August 2014
  • I-295 from Bragg Boulevard to All American Freeway, which was completed in December 2016

All American Freeway to Cliffdale Road

Referred to as Section CB, construction of I-295 from the All American Freeway to Cliffdale Road is complete. This section opened to traffic on Nov. 26, 2019, following a ribbon-cutting event​.

Cliffdale Road to U.S. 401/Raeford Road

The N.C. Department of Transportation awarded an $100.6 million design-build contract in June 2016 to the project team of Barnhill Contracting Co., Sanford Construction and HDR Engineering for work on Section CA, a 2.7-mile stretch from Cliffdale Road to U.S. 401/Raeford Road.

Design-build allows all aspects of a project from design through construction to be completed under a single contract.

Construction began in August 2017. Work also included replacing the Lake Rim Runoff bridge on Old Raeford Road over Bones Creek. The new bridge opened in December 2017.

This segment opened to traffic on Aug. 19, 2020​, allowing drivers to exit and enter at the new Raeford Road interchange. ​This contract also includes extending the Outer Loop south of Raeford Road to near Century Circle. The expected completion date for this entire segment is summer 2022.

U.S. 401/Raeford Road to Camden Road

Design and right-of-way acquisition are underway for work on Section B – U.S. 401/Raeford Road to Camden Road. This segment is scheduled to be awarded a construction contract in August 2022, with construction starting by that fall. Completion date will be in 2026.

Camden Road to I-95

In December 2017, a $129.7 million design-build contract was awarded to the Wilmington-based team of Balfour Beatty Infrastructure Inc., Branch Civil Inc., and STV Engineers Inc. The team will design and build Section A – Camden Road to I-95 near the Robeson-Cumberland county line. Construction began in the spring of 2019.

The widening of I-95 to a total of eight lanes between mile markers 37 and 40 will be included in this same project. The overall project, including the widening and the I-295 segment, is excepted to be completed by 2023.

The details for other I-95 widening or upgrade projects can be found on this page​.

9/22/2020 9:04 AM