​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Project Overview

​​​Planning and development are underway on a proposed project to improve approximately 10 miles of I-85 from the U.S. 321 interchange (Exit 17) in Gastonia to the N.C. 273 interchange (Exit 27) in Belmont.

To meet travel demands, I-85 will be widened from six to eight lanes in Gaston County. Interchanges, highway and railroad bridges will also be replaced to accommodate the expansion.

This project has been divided into three sections: 

1. Widen I-85 from U.S. 321 interchange (Exit 17) to west of N.C. 7 (Exit 23) & improvements to Cox Road/U.S. 29/74 in Gastonia

2. Widen I-85 from west of N.C. 7 (Exit 23) to east of N.C. 273 (Exit 27) & improvements to N.C. 7/U.S. 29/74 in Belmont

3. Replace two Norfolk Southern Railroad bridges, one P&N Railroad bridge and the bridge on Groves Street in Lowell

Project Funding

The first phase of this project is listed as Project I-5719A/U-6044 in the N.C. Department of Transportation's State Transportation Improvement Program and is funded for $587.7 and $65.3 million.

​I-85 widening from Exit 17 estimated cost*
​​Cox Road improvements estimated cost*
​Property acquisition

​$47,200,000

​$49,500,000
​Utility relocation
​$12,300,000​$1,500,000
​Construction costs​$528,205,000​$14,300,000
​Total cost ​$587,705,000$65,300,000

*Estimated costs subject to change​

The second phase of this project is listed as Project I-5719B/U-5800 in the N.C. Department of Transportation’s State Transportation Improvement Program and is funded for $567.8 and $41.9 million.



​I-85 widening from west of N.C. 7 (Exit 23) to east of N.C. 273 (Exit 27) estimated cost*
​Intersection of N.C. 7 & U.S. 29/74 in Belmont estimated cost*

​Property Acquisition 
​$38,400,000
​$18,600,000
​Utility relocation
​$47,900,000
​$3,700,000
​Construction costs ​
​$481.505,000
​$19,600,000
​Total cost 
​$567,805,000
​$41,900,000

*Estimated costs subject to change​

This third phase of this project is listed as project I-5719C in the N.C. Department of Transportation’s State Transportation Improvement Progra​m and is funded for $240 million. 



​Replacement of three railroad bridges and one highway bridge* 
​Property Acquisition 
​$5,000,000
​Utility relocation
​$2,600,000
​Construction costs 
​$232,400,000
​Total cost 
​$240,000,000

*Estimated costs subject to change