skip to main
Close Menu

Raeford Road Median (Fayetteville)

Project Overview

Planning and development are underway on a proposed project in Fayetteville to replace the open center turn lane with a median along 6.3 miles of Raeford Road (U.S. 401 Business) between Old Raeford Road and Robeson Street to improve safety.

The road’s reconstruction also will improve traffic flow and pedestrian access.

The project will be divided into three segments:
  • Segment A: Old Raeford Road to Bunce Drive 
  • Segment B: Bunce Drive to Glensford Drive
  • Segment C: Glensford Drive to Robeson Street
 
Each segment will be awarded separately as construction contracts, beginning with Old Raeford Road to Bunce Drive. 

Project Funding

This project is listed as Project U-4405 in the N.C. Department of Transportation's State Transportation Improvement Program and is funded for $147.8 million.

​Estimated Cost*
​Project development and design​$6,000,000
​Property acquisition​$51,600,000
​Construction costs​$90,200,000
​Total cost ​$147,800,000

*Estimated costs subject to change

Contact

Rusty Marsh, P.E.

Construction Engineer
Division 6

558 Gillespie St.
Fayetteville, NC 28301

Jason Salisbury, P.E.

Construction Staff Engineer
Division 6

558 Gillespie St.
Fayetteville, NC 28301

3/5/2019 10:37 AM