Close Menu

Project Highlights

The Winston-Salem Northern Beltway is divided into two parts – the Eastern Loop and the Western Loop – that are identified by the numbers assigned to them in the State Transportation Improvement Program, the N.C. Department of Transportation's 10-year plan that identifies the funding for transportation projects throughout the state and when they are scheduled for construction.

The Eastern Loop

Part of the future I-74 corridor, the 17.1-mile Eastern Loop (identified as U-2579), runs from U.S. 52 to I-74/U.S. 311. For construction purposes, it is divided into eight sections, each of which are in various stages, as shown in the following table.

​Section​Location​Project Status*​Map Link
​AA​I-74/U.S. 311 to I-40​Right of way - 2018
Construction - 2020
​Map 1
Map 2
​AB​I-40 to U.S. 421/Business 40​Right of way - 2018
Construction - 2020

Map 1
Map 2

​B​U.S. 421/Business 40 to U.S. 158​Under construction

Map 1
Map 2

​C​U.S. 158 to U.S. 311​Right of way - underway
Construction - 2018
Map
​D, E, F​U.S. 311 to University Parkway​Right of way - 2018
Construction - 2018

Section D map

Section E map

Section F map

​G​Hastings Hill Road bridge over U.S.
421/Business 40
​Complete​N/A

*Future dates are preliminary and subject to change


The Western Loop

The 17.4-mile Western Loop (identified as R-2247) runs from U.S. 158 (Stratford Road) to U.S. 52. For construction purposes, it is divided into 10 sections, each of which are in various stages, as shown in the following table.

​Section​Location​Project Status*​Map Link
​CC​Two bridge replacements over Muddy Creek​Complete​N/A
​CD​Upgrade of the Peace Haven Road/U.S. 421 interchange and the roads leading to it (within limits of Section CA)​Under Construction ​Map
​EC​Construction of interchange at U.S. 52 at N.C. 65​Under ConstructionMap
​EB​Construction of interchange at U.S. 52 and Winston-Salem Northern Beltway​Right of way - 2018
Construction - 2018
​Map
​A​U.S. 158 westward to south of I-40​Unfunded​N/A
​B​South of I-40 to south of U.S. 421 interchange​Right of way - 2027
Construction - 2027
Map
​CA​South of U.S. 421 interchange to north of U.S. 421 interchange​Right of way - 2027
Construction - 2027
Map
​CB​North of U.S. 421 interchange to Robinhood Road​Right of way - 2025
Construction - 2025
Map
​D​North of Meadowlark Drive/Robinhood Road to N.C. 67​Right of way - 2023
Construction - 2023
​Map
​EA​N.C. 67 to south of U.S. 52​Right of way - 2021
Construction - 2021
Map
​F​Deployment of Intelligent Transportation Systems (e.g., traffic signals, traffic cameras)​Unfunded​N/A

*Future dates are preliminary and subject to change

8/20/2018 11:56 AM

Back to top