I-40/I-440 Interchange & I-40 Widening

Project Overview

Planning and development are underway on two proposed projects to accommodate projected increases in traffic in Wake County over the next 25 years. Work would involve:

  • Adding lanes on I-40 from the I-440/U.S. 64 interchange to Lake Wheeler Road to improve the traffic-carrying capacity of I-40 (STIP I-5701)
  • Rebuilding the existing interchange at I-40/I-440/U.S. 1/U.S. 64 (STIP I-5703)

One of the nation’s fastest-growing counties, Wake County reached 1 million residents in 2014, and the population is expected to double by 2054.

This additional growth will increase traffic volumes by 55-70 percent on these roadways, which are important, high-volume corridors in North Carolina. I-40 and I-440 serve both commuter and long-distance traffic. U.S. 1 is also a primary local route as well as an important route for travel to Virginia and the mid-Atlantic region.

Project Funding

For funding purposes, this project is listed as two projects – I-5701 and I-5703 – in the N.C. Department of Transportation's State Transportation Improvement Program and is funded for a combined total of $179 million.

Additional Lanes on I-40 (STIP I-5701)

​Estimated Cost*
Construction costs​$25,500,000
Right of way acquisition and utilities
​$1,000,000
​Prior-year costs​$750,000
​Total cost ​$27,250,000

I-40/I-440/U.S. 1/U.S. 64 Interchange Reconstruction (STIP I-5703)

​Estimated Cost*
Construction costs​$130,000,000
Right of way acquisition and utilities​$21,000,000
Prior-year costs​$750,000
​Total cost ​$151,750,000

*Estimated costs subject to change

Public Input

NCDOT is seeking input from the public on this proposed project through the form of a short survey. To participate, click the button below.

Contact

Robert Hanson

Consultant Project Manager
Atkins

1616 E. Millbrook Road, Suite 160
Raleigh, NC 27609

Alison White

Project Manager
Highway Division 5

1545 Mail Service Center
Raleigh, NC 27699-1595

4/3/2019 8:45 PM