​​​​​​Construction of the first phase of the Complete 540 project is underway and when complete, will extend the existing Triangle Expressway (N.C. 540) between N.C. 55 Bypass and I-40.

Please note that construction activities are dependent on equipment and weather and are subject to change.

Activities scheduled to take place in the coming weeks, through May, include:

  • Clearing of land and installation of erosion control measures between:
     - Sunset Lake Road and Holly Springs Road
     - River Falls Drive and Sunset Lake Road
     - U.S. 401 and Old McCullers Road

  • Clearing of land where the project will cross Old Stage Road
  • Culvert construction, clearing of land, grading and installation of erosion control measures where the project will cross Fanny Brown Road
  • Clearing of land in preparation for bridgework and installation of erosion control measures where the project will cross Sauls Road
  • Periodic blasting of rock near East Williams Street and N.C. 55 Bypass
  • Ongoing work adjacent to I-40, including clearing of land, bridge construction, earthwork and installation of erosion and sedimentation control measures
  • Shifting traffic onto a new temporary ramp from I-40 West to U.S. 70 East/Bypass (Exit 309). This temporary ramp is scheduled to be in place for approximately 12-18 months

​​

5/22/2020 11:10 AM