Project Highlights

​​​NCDOT is building the Shelby Bypass in seven sections, as shown in the below chart.

​Section​Location​Length​Status​Details*
​AA​West of Peachtree Road to east of Kimbrell Road near Mooresboro​2 miles​Complete​Construction began in July 2013 and opened to traffic in September 2016.
​AB​East of Kimbrell Road to east of Plato Lee Road near Lattimore​1.9 milesComplete
Construction began in July 2014 and was completed in April 2018. A separate paving contract was completed in the fall of 2019. ​
​B​East of Plato Lee Road to east of N.C. 226 north of Shelby​2.6 milesComplete​
Construction began in July 2014 and was completed in April 2018. A separate paving contract was completed in the fall of 2019. 
​C​East of N.C. 226 to west of N.C. 150 heading northeast of Shelby​5.3 miles​Under ConstructionConstruction​ began in 2017 and should be completed in June ​2022.​
​D​West of N.C. 150 to U.S. 74 west of Long Branch Road, east of Shelby​4.1 miles​Under Development​Final designs are underway. Right of way purchasing is underway with construction beginning in 2024. 
​E​U.S. 74 west of Long Branch Road to west to Stony Point Road at U.S. 74 Business in Kings Mountain​2.6 miles
​Under DevelopmentFinal designs are underway. Right of way purchasing is underway with construction beginning in 2024.
​F
​East of Mooresboro to west of Stony Point Road at U.S. 74 Business in Kings Mountain
​18.5 miles
​In progr​ess
​Paving work along the length of the project is complete. Permanent vegetation establishment is ongoing.
​*Future dates are preliminary and subject to change ​ ​ ​ ​