NCDOT has heard community feedback requesting that portions of I‑77 South be capped or relocated underground. In response, the department is committed to a more in‑depth analysis of the feasibility of capping or placing part of I‑77 South underground.
As part of a previous evaluation, NCDOT previously reviewed and compared other major tunnel projects such as the Big Dig (Boston) and Alaskan Way (Seattle).
Based on those comparisons, relocating I-77 underground would cost billions of dollars per mile (10-20x NCDOT’s annual capital budget). Additionally, maintenance costs would be more than $50 million a year (nearly all of NCDOT Division 10’s annual maintenance fund for bridge and roadway maintenance, potholes, etc.). With the scope and scale of this project, an underground option could be even more impactful, depending on the construction methods that would be required to complete the work.
To determine possible annual maintenance cost for a tunnel, NCDOT considered these items:
- Power for continuous lighting and ventilation
- Ventilation fan operations and maintenance
- 24/7 staffing, monitoring, and control centers
- Fire and life/safety systems • Intelligent transportation systems, controls, and communications
- Drainage systems, pumps, inspections, and emergency response
Ultimately, a tunnel would not be financially viable for the I-77 South project.
The complexity of tunneling projects typically extends construction timelines to 5-10 years or more. This extended duration is largely due to the intricate processes.
Based on community feedback, NCDOT has started an additional in-depth analysis to further explore tunnel options near the uptown area.